We can always satisfy our respected customers with our good quality, good price and good service due to we are more professional and more hard-working and do it in cost-effective way for Sacrificial Shuttering, Girder beam formwork, Concrete Formwork Contractors, We, with open arms, invite all interested potential buyers to visit our web-site or get in touch with us immediately for further information and facts.
Cheap PriceList for Doka Tunnel Formwork - Pipe Gallery Trolley – Lianggong Detail:

Product Details

Pipe gallery trolley is a tunnel built underground in a city, integrating various engineeringpipe gallerys such as electric power, telecommunication, gas, heat and water supply and drainage system. There is special inspection port, lifting port and monitoring system, and planning, design, construction and management for the whole system have been consolidated and implemented. It is an important infrastructure and lifeline for a city’s running and management. To suit the market need, our company has developed the TC-120 pipe gallery trolley system. It is a new model trolley which ergonomically integrates the formwork system and trolley into a unity. The formwork can be installed and removed easily by adjusting the spindle strut of the trolley, without disassembling the whole system, thus achieving a safe and quick construction rationale.

Structure diagram


1

The trolley system is divided into semi-automatic traveling system and fully automatic traveling system.

1.Semi-automatic traveling system : The trolley system consists of gantry, formwork support system, hydraulic lifting system, adjustment support and traveling wheel. It needs to be dragged forward by a pulling device such as a hoist.

2.Fully-automatic traveling system: The trolley system consists of gantry, formwork support system, hydraulic lifting system,  adjustment support and electric traveling wheel. It only needs to press the button to move forward or backward.

Characteristics

1.The pipe gallery trolley system transmits all the loads generated by the concrete to the trolley gantry through the support system. The structure principle is simple and the force is reasonable. It has the characteristics of large rigidity, convenient operation and high safety factor.

2.The pipe gallery trolley system has a large operating space, which is convenient for workers to operate and related personnel to visit and inspect.

3.Quick and easy to install, fewer parts required, not easy to lose, easy to clean on site

4.After one-time assembly of the trolley system, there is no need to disassemble and it can be put into recyclable use.

5.The formwork of pipe gallery trolley system has the advantages of short erection time (according to the specific situation of the site, the regular time is about half a day), less personnel, and long-term turnover can reduce the construction period and cost of manpower as well.

Assembly process

1.Material checking

After entering the field, check the materials to ensure that the materials are consistent with the purchase list.

2.Site preparation

Before installing the TC-120 pipe gallery trolley system, the bottom of the pipe and the guide walls on both sides should be poured in advance (the formwork needs to be wrapped 100mm)

4

Site preparation before installation

3.Installation of bottom stringer

The adjustment support, the traveling wheel and the hydraulic lifting system are connected to the bottom stringer. Place the traveling trough according to the drawing mark ([16 channel steel, prepared by site), and extend the adjustment support beyond the hydraulic lifting system and the traveling wheel, install the connected bottom stringer. As shown below:


5

4.Mounting gantry

Connect the door handle to the bottom stringer. As shown below:

11

Connection of bottom stringer and gantry

5.Installation of top stringers and formwork

After Connecting the gantry to the top stringer, then connect the formwork . After the side formwork being installed and adjusted, the surface should be  smooth and flat, the joints are free of faults, and the geometric dimensions meet the design requirements. As shown below:


12

Installation of top stringer and formwork

6.Installation of the formwork support

Connect the cross brace of the formwork with the diagonal brace of the gantry to the formwork. As shown below:


55

Installation of the cross brace of the top formwork and the diagonal brace of the gantry

7.Installation of motor and circuit

Install hydraulic system motor and electric traveling wheel motor, add 46# hydraulic oil, and connect the circuit. As shown below:


7 (2)


7 (4)


7 (3)


7 (1)

Installation of motor and circuit

Application


Product detail pictures:

Cheap PriceList for Doka Tunnel Formwork - Pipe Gallery Trolley – Lianggong detail pictures

Cheap PriceList for Doka Tunnel Formwork - Pipe Gallery Trolley – Lianggong detail pictures


Related Product Guide:

To regularly increase the management program by virtue from the rule of "sincerely, good religion and high quality are the base of enterprise development", we greatly absorb the essence of linked products internationally, and constantly produce new goods to satisfy the calls for of shoppers for Cheap PriceList for Doka Tunnel Formwork - Pipe Gallery Trolley – Lianggong , The product will supply to all over the world, such as: Stuttgart, Bolivia, Austria, To achieve reciprocal advantages, our company is widely boosting our tactics of globalization in terms of communication with overseas customers, fast delivery, the best quality and long-term cooperation. Our company upholds the spirit of "innovation, harmony, team work and sharing, trails, pragmatic progress". Give us a chance and we will prove our capability. With your kind help, we believe that we can create a bright future with you together.
  • Hope that the company could stick to the enterprise spirit of "Quality, Efficiency, Innovation and Integrity", it will be better and better in the future.
    5 Stars By Dana from Mauritius - 2018.06.12 16:22
    After the signing of the contract, we received satisfactory goods in a short term, this is a commendable manufacturer.
    5 Stars By Eleanore from Sri Lanka - 2018.12.22 12:52
    Write your message here and send it to us